It has been a semester since day one you are in my class. Now it is the time to put your knowledge into test. I believe you are already prepared to answer questions in the final exam. The questions are not really hard but they test your understanding to understand the questions and able to translate them into answers. Don't worry as long as you study, you won't be having any problems answering them. Below I give you a video just to make you relax.....enjoy...
Monday, 29 October 2018
Wednesday, 17 October 2018
Attributable Profit
The concept of attributable profit relates to accounting for long-term contracts. Long-term contracts being ones which have not yet been completed, as at the accounting date.
The idea is to spread the total profit for the contract appropriately across the different accounting periods, for example a company's accounting years. This is achieved by booking an appropriate proportion of the total profit for the contract, in each year.
This appropriate proportion of the total profit is based on the attributable profit.
Attributable profit is defined as that part of the total profit currently estimated to arise over the duration of the contract, that fairly reflects the profit attributable to the work completed to date, as at the accounting date.
In calculating the total profit, allowance is also made for estimated remedial and maintenance costs and increases in costs, so far as they are not recoverable under the terms of the contract.
Relevant accounting standards include Section 13 and Section 23 of FRS 102.
taken form: https://wiki.treasurers.org/wiki/Attributable_profit
Tuesday, 9 October 2018
Contract Costing Exercise
The
estimated price of the contract is RM5,500,000.
Work
on the complex started on 1 October 2017. The accounting year ends on 30 June
every year.
The
following information is related to the contract for the year ended 30 June 2018:
RM
Materials
issued to site 550,000
Materials
received from supplier 485,000
Materials
returned to store 77,000
Plant
bought at cost (1 October 2017) 450,000
Wages
– paid 255,000
Subcontractor
charges – paid
108,000
Shares
of head office expenses 95,000
Additional
information:
1.
It is the company’s policy to depreciate
the non-current assets at 20% per annum.
2.
As at 30 June 2018:
i.
Unused materials - RM96,000
ii.
Accrued wages - RM55,000
iii.
Prepaid subcontractor charges - RM49,000
3.
Value of work certified is RM2,500,000 and
subjected to 10% retention money.
4.
Estimated future cost to complete the
contract is RM3,471,500.
Contract Costing
Definition of Contract Costing:
Contract costing is a specialized system of Job costing applies to long-term contracts as distinct from short-term jobs. Contract costing is mainly applied in civil construction and engineering projects, ship building, road and railway line contracts, construction of bridges etc.
Contract costing is a form of Specific order costing. It is applied to contracts where substantial time is taken to complete the contract and it falls into different accounting periods. However, a duration of exceeding one year is not an essential feature of a long-term contract. Some contracts with a shorter duration than one year should be accounted for as long-term contracts if they are sufficiently material to the activity of the period.
CIMA defines Contract cost and Contract costing as follows:
“Contract cost is the aggregated costs relative to a single contract designated a cost unit”.
“Contract costing is that form of specific order costing which applies where work is undertaken to customers’ special requirements and each order is of long-term duration”.
Features of Contract Costing:
The contracts for which Contract Costing is applied will have the following features:
(a) Contracts are undertaken to special requirements of the customers.
(b) Duration of contracts are relatively for a long period.
(c) Contract work is done on the sites unlike manufacturing under a roof.
(d) Contract work mainly consists of construction activities.
Accounting Procedure for Contract Costing:
If the numbers of contracts are more, a distinguishing number or name is given to each contract for accounting and administration convenience. A separate Contract Account is maintained for each contract.
All costs relating to contracts are charged to the respective Contract Accounts. In the contract cost structure, majority of the expenditure is of direct nature in the form of materials, wages, use of plant and stores, direct expenses etc., and only a small portion will be charged as apportioned overheads.
Accounting Treatment of Costs:
Accounting of each item of cost in contract accounts is discussed below:
1. Materials:
(a) All the materials purchased for the contract or any material sent to site is charged to contract.
(b) If any material is returned to stores or lying at site unused or materials transfers to another contract site is credited to the Contract Account.
(c) If materials are not required immediately, the materials may be stored and its cost is debited to Stock Account.
2. Labour:
All the labour employed or worked at site is treated as direct labour and all costs relating to them is charged to the Contract Account. The salaries and incentives of the administrative and supervisory staff of a specific contract is also charged to that specific contract.
3. Plant:
(a) When the plant is taken on hire, the hire charges are charged to Contract Account.
(b) If the plant is specifically purchased for the contract or plant was sent to site, the value of the plant is debited to Contract Account. The value of plant returned or remaining at site is credited to Contract Account. The balance between amounts debited and credited to contract represents the value of plant used at site.
(c) Sometimes the value of depreciation provided on the plant is debited to Contract Account instead of showing the value of plant issued to site and remaining at site.
4. Sub-Contract Charges:
Sometimes part of the contract work is given on subcontract basis and payments made on subcontract work is debited to Contract Account.
5. Overheads:
The general overheads and head office expenses are apportioned to different contracts on equitable basis, and the portion of overheads are charged to the Contract Account.
6. Difficulties in Cost Control:
Generally, contracts are big in size and the contract work is to be carried out at sites. Due to this some problems will arise concerning usage of material, labour utilization, supervision of labour, damage to plant and work, pilferage of materials and tools etc. This site based work makes it difficult to control the costs of the contract.
7. Surveyor’s Certificate and Retention Money:
In contract works, a surveyor or an architect or civil engineer is appointed to periodically visit the site for inspection of the work completed. He will issue a certificate mentioning the stage of completion of work and the value of the work completed to the date of issue of certificate. The payments will be released to the contractor by the contractee based on the said certificate.
Normally the payments will be released only to the certain percentage, say 80% of the work certified. The balance amount of work certified is retained by the contractee till the completion of the entire contract satisfactorily.
The amount so retained is called ‘retention money’. The contractee so retains to safeguard himself from the risks that may arise from the contractor. Usually the percentage of retention money is up to 20% of the amount of work certified.
8. Work-in-Progress:
The amount of work-in-progress includes the value of work certified and uncertified appearing in the Contract Account.
The work-in-progress is shown as Current Asset in the Balance Sheet as follows:
Materials at site, Plant at site are shown separately in the Assets side of the Balance sheet.
9. Costing of Running Contracts:
The long-term nature of contracts has necessitated to determine profit to be attributed to each accounting period. In the long-term contracts it is considered that their outcome can be assessed with reasonable certainty before their conclusion, the attributable profit should be calculated on a prudent basis and included in the accounts for the period under review.
The profit taken up should be based on Standard Cost Accounting principles. In case of Completed Contracts, all the profit that arise from the contract can be transferred to Profit and Loss Account.
But in case of Incomplete Contracts, only a portion of the profit is taken to the Profit and Loss Account depending on the extent of work completed on the contract because some provision is to be made for meeting contingencies and unforeseen loss. There are no hard and fast rules in calculation of profit to be taken to profit and loss account.
But in general, the following principles are followed:
(1) If loss is arrived on incomplete contracts, the entire loss is debited to Profit and Loss Account.
(2) Profit should be considered only in respect of work certified. The uncertified work should be valued at cost.
(3) Completion of contract is less than 25% of the contract price – No profit should be taken to Profit and Loss Account and the entire amount is kept as reserve for meeting contingencies.
(4) Completion of contract is upto 25% or more, but less than 50% of the contract price – In this case 1/3rd of profit, reduced in the ratio of cash received to work certified should be taken to the Profit and Loss Account. The balance will remain as reserve for meeting contingencies.
The formula is given below:
(5) Completion of contract is upto 50% or more, but less than 90% – In this case 2/3rds of profit ascertained as reduced by proportion of cash received to work certified to be taken to Profit and Loss Account, keeping the remaining amount in Reserve.
The formula is given below:
10. Costing of Contracts Nearing Completion:
Completion of contract is upto 90% or more (nearing completion):
In this case the profit to be taken to Profit and Loss Account is calculated by determining the estimated profit by using any one of the following formulas:
(a) Estimated profit x Work certified/Contract Price
(b) Estimated profit x Work certified/Contract price x Cash received/Work certified
Or
Estimated profit x Cash received/Contract price
(c) Estimated profit x Cost of work to date/Estimated total cost
(d) Estimated profit x Cost of work to date/Estimated total cost x Cash received/Work certified
(e) Notional profit x Work certified/Contract price
(The last formula is generally used when the estimated profit figure is not available.)
The balance amount of profit not transferred to Profit and Loss Account but kept as reserve for meeting contingencies is shown in the balance sheet assets side by deducting it from the amount of work-in-progress. It is carried down as a credit balance in the Contract Account itself, the work- in-progress being represented by the debit balance in the Contract Account.
taken from: http://www.accountingnotes.net/cost-accounting/contract-costing/contract-costing-definition-and-features-cost-accounting/10453
Variance Analysis Exercises
Hi there,
Using the same old example from the previous posting of Standard Costing, I expanded the exercises and it looks like below
Example:
Calculate the standard cost for oPhone.
Using the same old example from the previous posting of Standard Costing, I expanded the exercises and it looks like below
Example:
Setandet Kos Sdn Bhd manufactures mobile phone by the name of oPhone. Below is the budgeted cost information of oPhone for the month of October 2018 based on the budgeted production and sales of 5,000 units.
RM
Direct material:
Plastic casings (10,000 kg) 600,000
Wires (10,000 meters) 120,000
Direct labour (8,000 hours) 240,000
Variable overhead 100,000
Fixed overhead 60,000
The variable overhead cost is absorbed based on direct labour hours while the fixed overhead cost is absorbed based on number of units produced. The standard selling price of oPhone is RM1,200 per unit.
The actual data for
the month is as follows:
Units produced and sold 6,000
Selling price per unit RM1,000
Direct material:
Plastic casings purchased and
used 12,500 kg@ RM58 per kg
Wires purchased and used 10,750 meters @ RM10 per meter
Direct labour 10,000
hours @ RM22 per hour
Variable overhead cost RM120,000
Fixed overhead cost RM60,000
Analyse
the following:
i)
Direct
material price variance for plastic casings
ii)
Direct
material usage variance for wires
iii)
Direct
labour rate variance
iv)
Direct
labour efficiency variance
v)
Variable
overhead expenditure variance
vi)
Variable
overhead efficiency variance
vii)
Fixed
overhead expenditure variance
viii)
Fixed
overhead volume variance
ix)
Sales
margin price variance
x)
Sales
margin volume variance
Variance Analysis
Variance Analysis
Definition
Variance Analysis, in managerial accounting, refers to the investigation of deviations in financial performance from the standards defined in organizational budgets.
Explanation
Variance analysis typically involves the isolation of different causes for the variation in income and expenses over a given period from the budgeted standards.
So for example, if direct wages had been budgeted to cost $100,000 actually cost $200,000 during a period, variance analysis shall aim to identify how much of the increase in direct wages is attributable to:
- Increase in the wage rate (adverse labor rate variance);
- Decline in the productivity of workforce (adverse labor efficiency variance);
- Unanticipated idle time (labor idle time variance);
- More wages incurred due to higher production than the budget (favorable sales volume variance).
Types of Variances
Main types of variances are as follows:
- Sales Price Variance
- Sales Volume Variance
- Sales Mix Variance
- Sales Quantity Variance
- Direct Material Price Variance
- Direct Material Usage Variance
- Direct Material Mix Variance
- Direct Material Yield Variance
- Direct Labor Rate Variance
- Direct Labor Efficiency Variance
- Direct Labor Idle Time Variance
- Variable Overhead Spending Variance
- Variable Overhead Efficiency Variance
- Fixed Overhead Total Variance
- Fixed Overhead Spending Variance
- Fixed Overhead Volume Capacity & Efficiency Variance
taken from: https://accounting-simplified.com/management/variance-analysis/index.html
Sales Volume Variance
Definition
Formula
Sales
Volume Variance (where absorption costing is used):
Sales Volume Variance (where marginal costing is used):
Explanation
Example
Analysis
Favorable
sales volume variance suggests a higher standard profit or contribution than the
budgeted profit or contribution.
Reasons for favorable sales volume variance include:
Causes for an adverse sales volume variance include:
It is therefore important to investigate the sales volume variance by analyzing it further into sales quantity and sales mix variances in case where an organization sells more than one product.
Definition
Sales Price Variance is the measure of change in sales revenue as a
result of variance between actual and standard selling price.
Formula
Sales Price Variance:
=
|
(Actual Price - Standard Price)
|
x
|
Actual Unit
|
=
|
Actual Price x Actual Units Sold
|
-
|
Standard Price x Actual Units Sold
|
=
|
Actual Sales Revenue
|
-
|
Standard Revenue of Actual Units Sold
|
Explanation
Sales Price Variance can be
calculated in a number of ways as illustrated in the formulas given above. The
calculation of the variance is in fact very simple if you just remember the
objective of finding the variance, i.e. how much change in sales
revenue is attributable to the change in selling price from the standard?
Example
ABC PLC is a fertilizer producer which
specializes in the manufacture of NHK-II (a chemical fertilizer) and
ORG-I (a types of organic fertilizer).
Following information relates to the
sale of fertilizers by ABC PLC during the period:
Material
|
Quantity
|
Acutal Price
|
Standard Price
|
NHK-II
|
200 tons
|
$380/ton
|
$400/ton
|
ORG-I
|
300 tons
|
$660/ton
|
$600/ton
|
Sales Price Variance
shall be calculated as follows:
Actual
Price (a) |
Standard
Price (b) |
a - b = c
|
Unit Sold (d)
(tons) |
c x d
|
|
NHK-II
|
380
|
400
|
20
|
200
|
4,000
Adverse |
ORG-I
|
660
|
600
|
60
|
300
|
18,000
Favorable |
Total
|
14,000
Favorable |
Analysis
Favorable sales price variance suggests higher selling price realized
during the period than anticipated in the standard. Reasons for favorable sales
price variance may include:
- Decrease in the number of
competitors in the market
- Improved product
differentiation and market segmentation
- Better promotion and
aggressive sales campaign
Adverse sales price variance indicates that sales were made at a lower
average price than the standard. Causes for adverse sales price variance may include:
- Increase in competition in
the market
- Decrease in demand for the
products
- Reduction in price enforced
by regulatory authorities
Sales Volume Variance
Definition
Sales Volume Variance is the
measure of change in profit or contribution as a result of the
difference between actual and budgeted sales quantity.
Formula
Sales
Volume Variance (where absorption costing is used):
=
|
(Actual Unit Sold - Budgeted Unit Sales)
|
x
|
Standard Profit Per Unit
|
Sales Volume Variance (where marginal costing is used):
=
|
(Actual Unit Sold - Budgeted Unit Sales)
|
x
|
Standard Contribution Per Unit
|
Explanation
Sales Volume Variance quantifies the effect of a change in the
level of sales on the profit or contribution over the period.
Sales volume variance differs from other volume based variances
such as material usage variance and labor efficiency variance in
that it calculates not just the variance in sales revenue as a result of the
change in activity but it quantifies the overall change in the profit or
contribution.
The nature of the sales volume variance helps in forming a more
meaningful analysis of other variances in the preparation of the operating
statement. For example, the material usage variance needs
to take into account only the difference between the actual consumption
of material and the standard consumption of material for the
actual number of units sold since the sales volume variance already
takes into account the variation in material cost caused by the difference
between budgeted and actual sales volume.
Sales volume variance should be calculated using the
standard profit per unit in case of absorption costing whereas
in case of marginal costing system, standard contribution per
unit is to be applied.
Example
Wrangler Plc is a
manufacturer of jeans trousers and jackets.
Information relating to
Wrangler Plc's sales during the last period is as follows:
Trousers
Units |
Jackets
Units |
|
Budgeted
|
12,000
|
5,000
|
Actual
|
10,000
|
8,000
|
Standard costs and revenues per
unit of trouser and jacket are as follows:
Trousers
$ |
Jackets
$ |
|
Revenue
|
20
|
50
|
Direct labor
|
5
|
10
|
Direct Material
|
6
|
15
|
Variable Overheads
|
4
|
10
|
Fixed Overheads
|
2
|
5
|
Wrangler Plc uses marginal
costing to prepare its operating statement.
Sales Volume Variance shall be
calculated as follows:
Step 1: Calculate the standard
contribution per unit
As Wrangler Plc uses marginal
costing system, we need to calculate the standard contribution per unit.
Allocation of the fixed overheads may therefore be ignored.
Trousers
$ |
Jackets
$ |
|
Revenue
|
20
|
50
|
Direct labor
|
(5)
|
(10)
|
Direct Material
|
(6)
|
(15)
|
Variable Overheads
|
(4)
|
(10)
|
Standard contribution per unit
|
5
|
15
|
Step 2: Calculate the difference
between actual units sold and budgeted sales
Trousers
Units |
Jackets
Units |
|
Actual
|
10,000
|
8,000
|
Budgeted
|
(12,000)
|
(5,000)
|
Difference
|
(2,000)
|
3,000
|
Step 3: Calculate the variance
for each product
Trousers
|
Jackets
|
|
Standard contribution per unit (Step 1)
|
$5
|
$15
|
Actual Units Sold - Budgeted Sales (Step 2)
|
x (2000 units)
|
x 3000 units
|
Variance
|
$10,000 Adverse
|
$45,000 Favorable
|
Step 4: Add the individual
variances
Sales Volume Variance
($10,000 - $45,000)
|
=
|
$35,000 Favorable
|
Note: If Wrangler Plc used
absorption costing, sales volume variance would be calculated based on the
standard profit per unit (i.e. fixed costs per unit of output
will need to be deducted from the standard contribution calculated in Step 1).
Analysis
Favorable
sales volume variance suggests a higher standard profit or contribution than the
budgeted profit or contribution.Reasons for favorable sales volume variance include:
- Favorable sales
quantity variance (i.e. higher total number of units sold than budgeted)
- Favorable sales mix
variance> (i.e. higher proportion of the more
profitable products sold than planned in the budget)
Causes for an adverse sales volume variance include:
- Adverse sales
quantity variance (i.e. lower total number of units sold than budgeted)
- Adverse sales mix variance (i.e.
higher proportion of the less profitable products sold than anticipated in
the budget)
It is therefore important to investigate the sales volume variance by analyzing it further into sales quantity and sales mix variances in case where an organization sells more than one product.
Subscribe to:
Posts (Atom)